Automotive Parts Manufacturing
2024
Allur
NQDC
Location
Area
Parameters
Year
Client
General Designer
Classification
Industrial Facility / Automotive Industry
30 000 m²
Republic of Kazakhstan, Kostanay
Production of 70,000 parts sets per year
Group 1 focused on refining and detailing technological processes
Shaping of the common ideology of the object and general principles of its work; Determining the density of each production flow; Optimising of the technological chains; Designing the shortest possible logistical routes.
Group 2 handled equipment tasks
Selecting the necessary equipment as new solutions emerged; Defining optimal placement for its installation; Assessing its role in the technological process, interaction with other equipment, and integration with the building's engineering systems.
Group 4 addressed safety issues
Industrial safety; Labor protection; Environmental safety of the facility.
Group 3 connected all equipment with technological pipelines.
Group 5 coordinated the efforts of the remaining four groups
Monitoring new information and inputs; Instant adjustment of achievements of ongoing work; Process management.
To meet the deadlines, the team was divided into five parallel groups that constantly exchanged information and adjusted each other's work as new data became available.
Implementation
Develop the project within tight deadlines without compromising quality; Enable rapid reconfiguration of equipment and adjustment of technological processes; Propose technological solutions for the project.
Tasks
Regulatory framework of the Republic of Kazakhstan, including industrial safety; Allur's internal standards; internal standards of car and auto parts manufacturers (Chevrolet, Kia, JAC, Jetour, Hongqi, Skoda, and others).
Standarts
A project for a contact manufacturing facility specialising in a wide range of automotive parts.
Request
Illustration
Results
Thanks to this group division, we significantly reduced development time. The teams worked efficiently and seamlessly, promptly approving stages and results with the client. We successfully designed the equipment and technological processes for Allur’s facility.
Together with the client, we decided to implement multifunctional robotic equipment in production. The robots we proposed ensure the fastest and most efficient operations for Allur.